China Public Holidays 2026

Chinese New Year Shutdowns, Golden Week Blank Sailings, and Indian Customs Pre-Shipment Checklists
Plan Your China Orders Around the 2026 Holidays
A confirmed production and shipping plan is more useful than a last-minute promise.
China public holidays affect factory production, supplier replies, domestic trucking, warehouse receiving and freight bookings. The official holiday period is only part of the picture. Many factories slow down well before a major holiday and take several working days to return to normal capacity afterwards.
China Holiday Shipping Cut-Off Estimator
Select your target order dispatch month to see exact warehouse receiving cut-offs, vessel sailing deadlines, factory closure warnings, and risk levels.
New Year Holiday & Pre-CNY Rush
Official dates: 1 to 3 January 2026
15 January 2026 (for pre-CNY vessel departure)
20 January 2026 (warehouse receiving cut-off)
Mid to late January begins the massive pre-CNY factory slow-down
Severe container shortages and ocean freight rate spikes leading up to Spring Festival.
Strategic recommendation: Lock in container bookings 3 to 4 weeks in advance. Do not approve production after 20 January if you require delivery before March.
Official Mainland China Holiday Calendar 2026
Source: State Council of the PRC| Holiday | Official Dates | Adjusted Workdays | Business & Logistics Impact |
|---|---|---|---|
New Year Low Impact | 1 to 3 January | 4 January (Sunday) | Short disruption. Confirm warehouse receiving and domestic trucking availability. |
Spring Festival and Chinese New Year Critical Impact | 15 to 23 February | 14 February (Saturday) and 28 February (Saturday) | Largest annual shutdown risk. Factories slow production one to three weeks prior and restart gradually after the official break. |
Qingming Festival Moderate Impact | 4 to 6 April | None listed | Short break. Domestic trucking and logistics services operate on reduced schedules. |
Labour Day Moderate Impact | 1 to 5 May | 9 May (Saturday) | Production, transport and regional travel can experience heavy volume and holiday surcharges. |
Dragon Boat Festival Moderate Impact | 19 to 21 June | None listed | Short three-day break. Confirm factory pickup and container dispatch cut-offs in advance. |
Mid-Autumn Festival High Impact | 25 to 27 September | None listed | Factories and wholesale markets may close or operate with reduced staff immediately before Golden Week. |
National Day Golden Week Critical Impact | 1 to 7 October | 20 September (Sunday) and 10 October (Saturday) | Major nationwide shutdown and port congestion period. Book production completion, pickup and sea freight early. |
What Sourcing Customers Should Do: Order Timeline
| Timing | Recommended Sourcing & Logistics Action |
|---|---|
| Four to six weeks before | Confirm production schedule, packaging specifications, pre-shipment inspection and expected cargo-ready date. |
| Two to three weeks before | Book China factory pickup, consolidation warehouse receiving and ocean or air freight capacity. |
| Before factory deposit | Obtain written confirmation of holiday shutdown dates and production restart date from the factory manager. |
| During the holiday | Expect slower communications and limited factory, trucking, terminal and warehouse operations. |
| First week after holiday | Allow extra buffer for production backlog, migrant labour return, quality checks and transport congestion. |
Special Guidance for the Two Major Annual Shutdowns
Chinese New Year (Spring Festival)
Official holiday: 15 to 23 February 2026
- Do not plan only around the official 15 to 23 February holiday dates.
- Some factories reduce output one to three weeks earlier depending on migrant labour travel patterns and factory location.
- Confirm the last production date, last domestic pickup cut-off and realistic post-holiday restart date in writing.
- For time-sensitive commercial orders, complete production and third-party inspection well before the holiday period begins.
National Day Golden Week & Mid-Autumn
Official holiday: 1 to 7 October 2026
- Mid-Autumn Festival falls immediately before it on 25 to 27 September 2026, creating a sensitive consecutive planning window.
- Supplier communications, factory output, domestic trucking and warehouse receiving reduce significantly starting in late September.
- Cargo intended for October ocean dispatch should be finalized and collected before the cut-off dates agreed with our operations team.
- Air freight and express consolidations experience terminal congestion and peak capacity surcharges.
Yiwu and Wholesale Market Operating Guidance
The Yiwu International Trade Market is a permanent wholesale market, but individual shops, suppliers, export agents and consolidation warehouses follow different holiday arrangements.
Important: Do not rely solely on a general statement that the market is open.
During Chinese New Year and National Day, many individual booth operators travel home or operate with skeletal staffing. Buyers should obtain written confirmation from their specific suppliers and agents before booking international flights or market visits.
Customer Checklist Before Every Major Holiday
Verify every item on this checklist before releasing production balance payments or confirming shipping slots:
Sourcing Milestones and Notification Schedule
Recommended timing for internal order reviews, customer communications and container bookings:
| When to Take Action | Strategic Sourcing Milestone |
|---|---|
| Three weeks before Chinese New Year | Planning a China Order Before Chinese New Year |
| Two weeks before Labour Day | China Labour Day Holiday and Shipment Planning |
| Two weeks before Mid-Autumn Festival | Mid-Autumn Holiday Update for China Orders |
| Three weeks before National Day | Golden Week 2026: Confirm Production and Pickup Early |
| First working week after a major holiday | China Operations Have Resumed: Allow Time for Backlogs |
How LCL Global Helps You Navigate Holiday Disruptions
If your purchase order is planned around a China holiday, share the supplier contact details, expected cargo-ready date and packing specifications early. LCL Global coordinates China factory pickup, Yiwu or Guangzhou warehouse consolidation, customs documentation and compliant door to door delivery in India, subject to confirmed operating schedules.
Prepared 23 September 2026. Supplier, wholesale market, consolidation warehouse and ocean carrier schedules may differ from the national government holiday calendar. Always confirm the specific operating and receiving schedules relevant to your commercial order.